Here is an example we are dealing with :
We have a completed project with a good customer of ours, by completed, the work is complete, the payment is complete. The only thing is pending change order that is not yet accepted. Since we deal with the client's representative in that particular case, we are asked to keep this Change order active , on "the backburner" and it should be accepted and the work carried in the upcoming months.